Hi,
I have 2 servers: one enterprise and one slave running WSP. Now, I want to migrate both into one. All data now are in the slave server, so I want to get rid of the enterprise server, keep the slave and convert it to SolidCP.
From the migration guide, it shows how to upgrade the enterprise server. Is there anyway to do it for the slave server?
Thank you.
Hello,
The migration guide shows how to migrate Portal, Enterprise and Server modules (all 3)
Server module if on multiple server should be repeated on all servers.
If you want to get rid of the enterprise server the most easy way is to make a fresh Enterprise installation on the new server, then convert the web.config of Enterprise with the settings of the old enterprise, and identical for the enterprise\bin\ scheduler config.